How much steel required in 900 square feet slab?.. Answer / prakash 1st conformer its residential building or commercial 1.5 to 2.0kg/sft and 3.5 to 4.0 kg/sft
Vacuum concrete — a higher quantity of water is added to the concrete mix, and then the mixture is poured into the formwork. Permeable concrete — water is able to pass through it. Used in areas where storm water is an issue. Sprayed concrete — it is fabricated in the same way as ordinary concrete, but the way of placing it differs. It is ...
step 2 :-calculate wet volume of concrete by multiplying area and thickness of slab = 100 sq ft × 0.334 ft = 33.4 cu ft, hance wet volume of concrete is equal to 33.4 cu ft. step 3 :-we know that dry volume of concrete is …
Multiply area and thickness to calculate wet volume of concrete. Volume of 700 sq ft of RCC slab at 4 inches thick in m3 = (700 × 4/12) ÷ 35.32 = 6.6 m3. At 4″ thickness, the total quantity of steel required for 700 sq ft (6.6 cubic meters) RCC roof slab is equal to = 85 × 6.6 = 561 kg. This means, 562 kg of steel is required per 700 sq ft ...
Required Steel quantity for 1000 sq ft roof slab. According to the thumb rule 0.5% to 1% steel required for roof slab. But we will take the average of 0.5% and 1%, which is 0.75%. Steel density = 7850 kg/m 3. Steel quantity for 1000 sq ft slab in kg = Steel volume × dry concrete volume × steel density. = 0.75/100 × 18.168 × 7850
The amount of wall putty required for 100 sq ft (square feet) area for 2 coats is about 7-8 kg. Typically wall putty requires 7-8 kg putty per 100 square feet for 2 coats. To calculate the amount of putty for 100 sq ft, divide it by putty coverage per sq ft i. …
1. Steel requirement for RCC beam = 1 to 2% or 78.5 kg to 157 kg/m³. 2. Steel requirement for RCC column = 0.8 to 6 % or 62.8 kg to 471 kg/m³. 3. Steel requirement …
An average of 5,250 to 6,000 kg (or 5.25 to 6 tons) of steel required for 1500 sq ft house, according to the rule of thumb. A typical home requires 3.5 to 4 kg of steel per square foot, therefore a 1,500-square-foot home would require between 5,250 and 6,000 kg of steel to construct.
The next step is to convert this area of steel into weight. The density of steel is approximately 490 lbs/ft^3 (7850 kg/m^3). So, the weight of steel required for the 1 sq ft roof slab will be 0.00185 * 490 = 0.9045 lbs (0.41 kg). In conclusion, for a 1 sq ft (0.09. Steel required for 1 sq ft RCC roof slab 5 inch thickness
Steel required for 1000 sft india. Concrete Materials Calculators : … » More detailed! how much cement is required for 100 sft plastering of ratio 1:4. how much cement is required for 100 sft plastering of ratio 1:4 Interview Questions » More detailed! » More detailed! How much steel is required per sq foot of any RCC ...
How to use this tool? How to Estimate Materails in a slab | Best Tools to estimate Online. Watch on. Standard Data used in this Calculator. Added 54% extra mortar to convert wet …
Thumb rule to calculate steel in slabs is 3.5 kg to 4 kg/sq. ft of built-up area. On the whole, approximately 3500 kg to 4000 kg of steel is required to build a 1000 square feet structure. This is one of the most basic important information that one must be aware of before building his/her own dream house.
Sand quantity = 3/4 × 0.3m3 × 35.3147 = 8 cubic feet, thus you will need 8 cft or 0.225m3 of sand for 1m3 brick masonry by taking 1:3 mix. 8 cu ft or 0.225m3 of sand quantity are required for 1 cubic metre of brickwork by …
Steel reinforcement – 100 Kg including cutting and laying: ... 90 Sft: Carpenter-2.25 Foreman- 0.2 Helper- 2.25: Shuttering Work: 11 Sqm: Bar Bender – 1 Nos ... WHY DONT WE DO CEMENT AND SAND BRICKES REQUIRED FOR 1SFT…IF NO GIVE AN EXAMPLE FOR 1SFT 1:6 CM. siva prasad 2 years ago Reply.
Consider 2 % wastage during transportation storage & work. 2 % of 376 = 8 nos. Total no of bricks = 376 + 8 = 384. That's 384 pcs of bricks are required for 100 square feet (10×10 sq ft) and a 4.5 inch thick brick wall. A typical 4.5 inch brick wall requires 384 pcs bricks per 100 square feet (sq ft).
Thumb rule to estimate Steel quantity of above slab = Volume of Concrete x Density of Steel x % of Steel of Member. Steel weight required for above slab = 3 x 7850 x 0.01 = 235 Kgs. For accurate estimation, you can refer to Bar Bending Schedule. 4. Thumb Rules For Shuttering Work. Shuttering costs are taken as 15-18% of the total …
Volume of 1 sq.m (square meter) of RCC slab at 100 mm thick in m3 = (1 × 0.1) = 0.1 m3 At 100 mm thickness, the total quantity of steel required for 1 sq.m (0.1 cubic meter) RCC roof slab is equal to = 80 × 0.1 = 8kg. This means, 8kgof steel is needed per sq.m (square meter) of 100 mm thick … See more
Thumb rule for Steel required for RCC slab is 80 kgs/m3, then quantity of steel required for 1000 sq ft ( 11.8 m3) rcc slab is equal to = 80 × 11.8 = 950 kgs. At 5″ thickness, the total amount of steel required for 1000 sq ft (11.8 cubic meters) of RCC roof slab is equal to = 80 × 11.8 = 950 kg. This means, 950 kg of steel is needed per ...
At 6″ thickness, the total quantity of steel required for 900 sq ft (12.74 cubic meters) RCC roof slab is equal to = 80 × 12.74 = 1020 kg. This means, 1020 kg of steel is needed per 900 sq ft of 6-inch thick RCC roof slab. As per thumb rules and generals guide line, for a 900 sq ft rcc roof slab at 4 inch thickness, generally you will need ...
Consider,plastering ( Cement and sand)thickness = 10mm 100 Sqft = 9.29 Sqm-----Wet Mortar volume= 9.29 X 0.01Cum =0.0929 Cum Dry Mortar volume = 0.0929 X 1.15 =0.106835 Cum Cement = 1/4 X 0.106835 X 1400 Kg =37.392 Kgs (Volume of cement is ignored ) Hence for 100 Sqft area,and 10mm thick plastering the cement quantity …
RCC CALCULATOR. Estimate RCC/ Reinforced cement concrete quantities cement, sand and aggregate.. Calculate. Results: Cubic Feet. Cubic Meters.
The approximate Steel consumption per sq.ft built up area (BUA) is 4 kg per sqft (for low rise construction i.e., less than 4 floors of construction). Steel contributes the most among all individual materials, about 25% of …
The ratio means for every 130 kg concrete 100 kg of steel is needed. 100 kg of steel strengthen the structure in RCC. Failing this ratio of steel to concrete would cause weakening the structure and fatal cracks to it. Based on the construction type ratio of TMT Steel Bar to Concrete is: Civil Construction / Heavy Industrial Construction = 130 kg/m3
Multiply area and thickness to calculate wet volume of concrete. Volume of 1200 sq ft of RCC slab at 4 inches thick in m3 = (1200 × 4/12) ÷ 35.32 = 11.33 m3. At 4″ thickness, the total quantity of steel required for 1200 sq ft (11.33 cubic meters) RCC roof slab is equal to = 80 × 11.33 = 906 kg. This means, 906 kg of steel is needed per ...
Volume of 1400 sq ft of RCC slab at 6 inches thick in m3 = (1400 × 6/12) ÷ 35.32 = 19.82 m3. At 6″ thickness, the total quantity of steel required for 1400 sq ft (19.82 cubic meters) RCC roof slab is equal to = 80 × 19.82 = 1585 kg. This means, 1585 kg of steel is needed per 1400 sq ft of 6-inch thick RCC roof slab. As per thumb rules and ...
Raw Material Calculator for Construction. Calculate the approximate quantity of construction material required for a single storey load bearing building.*. Enter Area. *Assumptions: 1. Load bearing brick wall thickness of 23cm (9 inches) in cement mortar 1:6. 2. Plaster in cement mortar 1:4.
Total Cost = 9,00,000 Rs. / 1000 sq. ft. Construction area. The construction cost estimator/calculator helps to finalize the approximate amount of cost & quantity of material required for constructing a home.The calculator estimates the approximate cost and quantity of Cement, Sand, Aggregate, Steel, Paint, Flooring, Tiles, Bricks, Fittings ...
Steel for door beam = 158 + 61 = 219 kg. 219 Kg of Steel required in door beam of 1000 square feet of house. 5) roof wall beam size for external wall = 225 mm × 200 mm. Overall length for external beam = 130 ft = 39000 mm. Steel = 0.225 × 0.2 × 39 × 120 = 211 Kg. Roof wall beam size for internal wall = 125 mm × 200 mm.
If the Plinth area is 100 Sq.ft (10 x 10) and the required concrete volume is 100 x 0.04 = 4 m3 with M5 mix ratio means. Now from the below table which is for 1 m3. Required …
The thumb rules in civil engineering are as follows, 1. Thumb Rule for Concrete Volume. The volume of concrete required = 0.038 m3/square feet area. Example:- If Plan Area = 40 x 20 = 800 Sq. m. So, for the plan area of 800 Sq. m. the area the total volume of concrete required. = 800 x 0.038m3 = 30.4m3.
This concrete calculator allows you to estimate how much concrete you need for a specific area and how many bags of concrete are required for this space, …
Steel required for 100 sq ft roof slab – We we have given area of RCC slab is equal to 100 square feet and thickness of RCC slab is 4 inch, 5 inch and 6 inch thick. 1) Steel required for 100 sq ft slab 4 …
For office, school building, steel may increase marginally due to live load condition,thickness of slab will be 5 inch thick, so for the plan area of 600 sq ft total volume of concrete required = 600 × 0.416 ÷ 35.3147 = 7.067 m3, as per thumb rule 80 kg to 90 kg of steel are required per cubic meter volume of concrete, so as 80 kg × 7.067 ...
The cost varies between Rs 420 – 450 per Square foot and about 23 % of the total construction cost. Civil works – This is the highest construction cost estimation head involved in this construction phase which includes excavation, footings, RCC work, Blockwork, plaster, etc. The cost varies between Rs. 980 – 1000 per Square feet and …